Completed / operationalActivation Area trunk infrastructure
The first 22.54 sq. km phase of Dholera SIR (TP 2A and 4A) has its trunk infrastructure in place: about 72 km of internal roads, underground utility corridors, power from two distribution companies, water treatment, sewage and wastewater lines, and ICT ducts.
Status as of Nov 2026 · Source
Completed / operationalAhmedabad–Dholera Expressway
The 109 km access-controlled expressway, built under Bharatmala, opened to the public on a trial basis in February 2026, with a formal inauguration scheduled for 31 March 2026. It cuts the drive from Ahmedabad to roughly 45 minutes and runs past the airport site at Navagam.
Status as of Mar 2026 · Source
Approved / in forceSemiconductor SEZ notified
The central government notified a Special Economic Zone for the Tata–PSMC semiconductor project at Dholera in April 2026.
Status as of Apr 2026 · Source
Under constructionDholera International Airport
A greenfield airport at Navagam with a 3,200 m first runway. The Union Aviation Minister reported about 80% completion in July 2026, a calibration flight has landed, and in October 2026 the Gujarat Chief Minister said it would be operational by the end of the year. Treat as under construction until scheduled flights begin.
Status as of Oct 2026 · Source
Under constructionHospital, school and food court
In February 2026 DICDL invited operators to run a multi-specialty hospital, a school and a food court built inside the Activation Area – a step from pure infrastructure towards a liveable city.
Status as of Feb 2026 · Source
PlannedFull 920 sq. km city
Dholera SIR covers 920 sq. km, of which about 422 sq. km is developable under Town Planning Schemes. Development beyond the Activation Area is phased over many years.
Status as of Nov 2026 · Source